Case History 1- Assembly
From a derelict industrial building to a high-tech production facility in 12 weeks
Opportunity
A small defence contractor needed a production partner to create a bespoke manufacturing facility for a low volume, high-value, security-sensitive product currently in development. The production facility needed to be ready as soon as testing was complete.
Brief
Find a site of 10,0000-20,000 square feet located within a specified area of the UK and prepare it for production. Find and train staff and be production-ready in 8-12 weeks.
Task
The available sites were not suitable for the task, so we needed to convert a rundown warehouse into a modern production facility.
This involved:
Building works
Lighting
Heating
Fire regulations
Contracts for:
Security
Building maintenance
Waste
Power
Staff Recruitment:
Managers
Admin
Accounts
Stores
QA
Assembly leaders
Assembly technician
Software installation technicians
Test engineers
Security:
CCTC, Door entry
Security monitoring service
Police monitoring
Staff monitoring
Staff security clearance
Factory Layout:
Office fit out
Canteen
Staff rest area
Stores
Kitting area
Rework area
Works shop
Clean room
Production area
QA
Testing
Product storage: goods in and out, work in progress.
Hardware:
Source specialist equipment
Hire forklift
Lockers
Systems:
Admin systems
Stock control system
Human resources systems, Contracts
How we achieved the task
Running tasks in parallel
Site search
Site preparation
Recruitment
Equipment purchase
Service commissioning
Contractors: Electrical, Building, Security
Security operating instructions
Engineering of custom equipment
Systems creation and management
Training
Design team
Developed a build plan for the product from the CAD model
Created CAD models for the assembly areas
Engineered bespoke equipment
Skills and attitude
Skilled people
Can do approach
Management teams flexibility
Forecasting bottlenecks
Predicting potential failures
Conclusion
Creating a custom manufacturing facility in 12 weeks is not typical for most companies. It usually takes 12 to 18 months. Many projects like this fall outside the scope of prime contractors, as they may not have the resources to achieve a fast turnaround. As a small group of specialist problem solvers, we can get the job done and deliver projects that would be thought impossible.